Operation
Power On the System
WARNING
- Before doing electrical connection, please ensure the PV switch & all AC and BAT circuit breakers in the system are switched OFF and cannot be reactivated.
- Never power on the energy storage system without the correct and reliable installation and electrical connection.
Switch on the battery circuit breaker which is at the lower left of the inverter.
Switch on the battery circuit breakers of all batteries (located on the left-hand side of the battery).
Switch on the AC circuit breaker between the grid port of the energy storage inverter and the mains grid (this AC circuit breaker should be labelled Main Switch Battery ESS Supply or similar).
Switch on the AC circuit breaker between the backup port of the energy storage inverter and the loads (this AC circuit breaker should be labelled Main Switch Battery ESS Backup or similar).
Switch on the PV switch at the left middle of the inverter if there is PV string directly connected to the energy storage inverter.
Switch on the AC circuit breaker (if there is any) between any separate PV inverter and the mains grid. These separate PV inverters are also referred to as “AC-coupled PV inverters”.
Power Off the System
WARNING
After the energy storage system is powered off, the remaining electricity and heat may still cause electric shocks and body burns. Please put on protective gloves and operate the product 5 minutes after the system is powered off.
Switch off the AC circuit breaker between the ESS inverter and the backed-up loads.
Switch off the AC circuit breaker between the ESS inverter and the mains grid.
Switch off the PV DC Isolator(s) between the PV strings and the ESS inverter if there are any.
Switch off the PV switch on the lower left of the ESS inverter (if there are PV strings directly connected the ESS inverter).
Switch off the battery circuit breakers of all batteries.
Switch off the battery circuit breaker which is at the upper left of the inverter.